Section B01 Section B02 Section B03 Section B04 Section B05 Section B06 Section B07 Section B08 Section B10

B09 News

The Pennsylvania Department of Transportation (PennDOT), in cooperation with the Federal Highway Administration (FHWA), plans to reconstruct U.S. Route 22 from west of the S.R. 0982 intersection in Derry Township Westmoreland County to Township Road 968 intersection in Derry Township Westmoreland County.

The proposed project consists of the upgrade of the existing U.S. Route 22. This portion of the U.S. Route 22 reconstruction will upgrade S.R. 0022, Section B09 from a three and four-lane facility to all four-lanes with provisions for a fifth turning lane at appropriate locations. In general, the improvements will widen the roadway to two lanes in each direction. A concrete median barrier will be constructed and left turns will be restricted to areas where openings in the concrete median barrier are provided. The distance between openings in the median barrier, where turnarounds can be negotiated, will be at approximately 2 mile intervals. A traffic signal will be installed at the Route 22/982 intersection.

Progress continues along S.R. 0022, Section B09 in Westmoreland County following the approval of Preliminary Design. PennDOT and the project team are proceeding with the Final Design including utility coordination, right-of-way plans, roadway plans, traffic control plans, traffic signal plans and structure plans.

DESIGN FIELD VIEW

A Design Field View meeting was held on May 13, 2003 on site. During the meeting the Preliminary Design plans were presented for review. PennDOT/FHWA approved the Preliminary Design plans on July 11, 2003. The project team is currently working on the Final Design plans.

UTILITY COORDINATION MEETINGS

A Utility Coordination meeting was held at the Derry Township Municipal Building on May 19, 2006. The purpose of this meeting was to present final design plans to the affected utility companies and to assist them with any additional information they may need to perform their final relocation designs.

Each of the affected companies received Final Design Plans prior to the meetings for their review. Areas of concern were discussed with each representative. Relocations will be evaluated on a case-by-case basis to ensure that the clear zone requirements are met, as well as access requirements of the utility companies.

RIGHT-OF-WAY PLANS

The final right-of-way plans will be submitted to PennDOT District 12-0 in the near future. Currently, right-of-way is being acquired for the project.

ENVIRONMENTAL CLEARANCE

A re-evaluation of the Environmental Assessment began in April 2003 and was approved December 1, 2004. The original Environmental Clearance was received February 24, 1999 for S.R. 0022, Sections B07, B08, B09, B10, Salem and Derry Townships, Westmoreland County, PA.

PUBLIC PLANS DISPLAY Public Plans Display Recap

 As work to improve U.S. Route 22 in Westmoreland County continues, PennDOT District 12-0 and the Federal Highway Administration (FHWA) conducted a Public Plans Display for the S.R. 0022, Sections B09 and B10 projects on August 13, 2002 at the Derry Area Middle School in Derry Borough, Westmoreland County.

The purpose of the open house meeting was to inform the community about important design elements of both projects, including the placement of median barrier and the location of turn lanes, signalized intersections and jughandles to enhance safety and mobility, and to provide an opportunity for community input.

EMERGENCY SERVICE PROVIDERS MEETING

Following the Public Plans Display, a special meeting was held for Emergency Service Providers on August 28, 2002 in Derry Borough, Westmoreland County.  The purpose of the meeting was to present current plans for both the S.R. 0022 Sections B09 and B10 projects to the local emergency service providers, and to solicit their feedback on the proposed improvements. 

For details on the content and results of these meetings,
follow this link
.
 

Travel Alerts