Section
B08
 |
|
Proposed
Project Schedule |
| Environmental
Clearance |
February
24, 1999 |
|
(Re-evaluated 12-1-04) |
| Begin
Final Design |
March 2001 |
| Begin
Right-of-Way Process |
March
2003 |
| Bid
Construction Contract |
December
2005 |
| Begin
Construction |
May 2006 |
| Completed
Project |
Fall 2009 |
|
|
Travel Alerts |
 |
 |
 |
 |
| |
|
|
|
|
|
|
|
|
|
All dates listed under the
project schedule are tentative and subject to change.
No property should be considered
acquired until the filing of a declaration of taking or the conclusion of
a sale in lieu of condemnation.
|