Major
construction of Section B08 was completed in September 2009.
All road closures and detours have been removed.
Please go to the Photographs
link to view photos of the completed section.
The U.S. Route 22, Section B08 project was let on December 15,
2005. Golden Triangle Construction was the low bidder and was
awarded the project for a contract amount of $35,408,791.
Approximately 4.3 miles of Route 22 were reconstructed with four
new concrete traffic lanes with a median divider, new drainage, and
several jughandles to allow traffic to switch directions between
westbound and eastbound lanes.
The
reconstruction of U.S. Route 22, Section B08 will impact 2.05 acres
of wetlands, which will be replaced at a
wetland mitigation site
on property owned by the U.S. Army Corps of Engineers in Derry
Township.
 |
 |
|
Western
section limit looking east |
Eastern section limit looking west |
|